Lime Pointing ~ time trial

Category: Barn Conversion Journal November 2nd, 2010 by mbc

I’m trying to get the pointing finished this year, but it drags on and I could do with a change of scene. So although I’ve not yet finished the northern gable end I decided to finish the more straight-forward and visible back wall. I’d completed all along the bottom of the back wall – up as high as I was able to reach on a step ladder and so to finish the top I’ll need to use an extending ladder.

(As a slight aside, pointing from a ladder isn’t as awkward as it sounds – you can rest the mortar hawk and any tools you’re not using on the rungs of the ladder ahead of you and so can point one handed – which makes a change.)

But, how long would it take me?

To answer that question (and make a probably misguided attempt to make pointing exciting) I decided to undertake a lime pointing time trialhow much could I get finished in one hour? (You’ve got to give me credit for a least trying to make things exciting…)

Here are my results:

Before:

From Pointing

One hour later:

From Pointing

Now I realise that my results don’t exactly standout from these pictures (no I didn’t just move a ladder during the hour – if you look closely you can see the grey / brown pointing in the joints between the stonework on the second picture). I’ll take another picture next weekend after the mortar has dried to the off-white that the dry mortar lower on the wall is [See below – picture added November 2010]. I managed to point from the right hand corner to the left side of the ladder, with a couple of patches needing some more work and pointing started on some patches to the left of the ladder. To save some time I used a mortar gun to fill some of the deeper / wider joints and placed a few pinning stones in wide joints – which eats up some time.

My conclusion was that pointing at this rate I would need 8 to 10 hours to finish the back wall. That would be a long day’s work, or more likely a day and the following morning. I can then finish the top of the northern gable end in my own time…

We’ll see…

From Barn Conversion 2010

If you enjoyed that post, then read these…

Lucious Lime
After my ‘introduction to lime’ course I have a great fear that I may be joining the ranks of sustainable / healthy / traditional / vernacular building fanatics – those…

tag: ‘lime

Building Progress ~ May 2009
May has been about two things – painting and tiling.

category: ‘Barn Conversion Journal

Building Progress ~ September 2010
Seems like I’ve been repointing for ever.

tag: ‘repointing

Posted in Barn Conversion Journal | 1 Comment » « Leave Yours
Tags: ,

One Response

  1. Building Progress ~ October 2010 | my barn conversion Says:

    […] Lime Pointing ~ time trial […]

Leave a Comment

Please note: Comment moderation is enabled and may delay your comment. There is no need to resubmit your comment.