Around an ongoing barn conversion project, this website draws together advice, information and references to aid all would-be and current barn and non-residential building converters and renovators.

Our approach takes on board 'healthy house', sustainable, ecological & environmental concepts to as great a degree as timescales and budgets allow.

my barn conversion
Latest Posts

BREEAM ~ Building Research Establishment Environmental Assessment Method by mbc on May 11th, 2008

Microgeneration installations now 'permitted developments' by mbc on May 6th, 2008

Transition Town Llandeilo by mbc on May 4th, 2008

My Favourite Things ~ ‘Stone Wall’ by mbc on May 1st, 2008

Building Progress ~ April 2008 by mbc on April 29th, 2008

Latest Comments

On Peak Oil ~ what is it & what bearing does it have on green building? by Transition Town Llandeilo | my barn conversion on May 4th, 2008

On Where have all the builders gone? by mbc on April 28th, 2008
That's a bit of a 'how long is a piece of string' question miss dee ennis and obviously depends on location, the approach you take to the project (architect / main contractor / self-managed with sub-contractors etc.

On Where have all the builders gone? by miss dee ennis on April 28th, 2008
I am thinking of buying a barn for myself and would be gratfull if someone could give me a ballpark figure as to how much this is likly to cost .

On Project Management ~ Basecamp by Attention to detail… April 2008 update | my barn conversion on April 15th, 2008

On Heating & Hot Water - a solution? by Building Progress ~ March 2008, week 3 & 4 | my barn conversion on April 8th, 2008

    Search MBC

thumbnail
thumbnail
thumbnail

Meta

Building Progress ~ December 2007, week 3 and 4

December 31st, 2007 by mbc

Merry Christmas and a Happy New Year to you all!

Obviously with nasty old Christmas getting in the way (!) progress has slowed a little, but not to the extent I would have expected.

The beams are looking great and have been completely embedded in the wall - the walls have been rebuilt where the holes where pushed through to allow the beams to be put into place. Apparently, each beam weighs around three quarters of a tonne, enough to make the machine that was used to lift them lean alarmingly before getting the job done!

floor joists
The two windows that we’re putting through on the ground floor gable-end have been measured up and partially cut through. I was worried that they’d be too big, but the size looks about right. The damp problems in the wall have been further confirmed by the builder when cutting the windows out and I’m currently figuring out what to do - I have an idea or two of which more in the future…

Major progress has been made in starting construction of the first floor in the main part of the barn. Last I saw of it, the joists that run lengthwise through the barn, supported by the oak beams had begun to be put into place and the feel of the new building has begun to establish itself - exciting times.

Finally, the opening between the two ground floor rooms of the barn has been fully established and the retaining walls strengthened. There have been a couple of difficulties in getting the levels of the reclaimed oak lintels correct as there are two steps up into the kitchen and a conundrum to be solved in getting the various ceiling, lintel and floor levels correct, but I think we’ve got there, hopefully without the opportunity of me banging my head.

If you enjoyed that post, then read these...

Here we go... on January 28th, 2007
Having claimed that the ball was rolling back on the 28th June 2006 only to spend six months to-ing & fro-ing, waiting for utility companies and solicitors to get their acts together, the ball really has started rolling.

Building Progress ~ April 2008 on April 29th, 2008
I can't believe that April is drawing to a close and I've not managed an update since the end of March.

Building Progress ~ November 2007, week 3 and 4 on December 10th, 2007
Through to the end of November progress has been mainly on filling back in what has been taken out! .

Where have all the builders gone? on July 17th, 2006
Having embarked on this crazy journey I thought we should try to firm up on exactly what it will cost.

Building Progress ~ December 2007, week 1 and 2 on December 17th, 2007
The first of the structural elements that will form a finished part of the building have been installed.

Posted in Journal of my barn conversion |

4 Responses

  1. Graham Says:

    Happy New Year! Wow - well now we’ve found the site we’ll be keeping a close eye :) Looks great…! G&D

  2. mbc Says:

    Great to hear from you Graham - keep tuned in!

  3. Lynds Says:

    Happy new year - don’t go blaming your hangovers on your lintels now ;-)

  4. mbc Says:

    Happy New Year! - the bruises are healing at last…

Leave a Comment

Please note: Comment moderation is enabled and may delay your comment. There is no need to resubmit your comment.